  • The client wanted to redevelop a former Council leisure centre into a 72-apartment Extra Care facility at Stirchley, Telford.
  • The scheme was designed to include external gardens, rooftop gardens, and a café/bistro that would all be available for use by members of the local community.
  • The scheme was planned as 100% affordable, with all residents to be from the Council Housing Waiting List.

What we did

  • Sarah, in her role as Planning Partner at Rapleys LLP, managed a team of consultants including architects, transport, ecology, noise, drainage, and landscape experts to submit a full application for the scheme.
  • The process involved pre-application discussions, negotiations with the Local Planning Authority, and submission of revisions to the design.
  • Presented to the Planning Committee, to ultimately secure planning permission in line with the Officers' recommendation for this specialist type of housing.
  • Submission of discharge of condition applications followed.

How we added value

  • We worked to a tight timeline, bringing everything to fruition within the 13-week determination period.
  • Through working closely with a receptive Local Authority, the consultant team achieved the granting of planning permission in 2023.
  • Construction was able to commence immediately after the pre-commencement conditions were discharged, and the facility formally opened to its new residents in Spring 2025.